EnergyNews wire, 9 Nov 2026

Panamint's 1.2 GW Big Rooter solar project in Texas secures $1.8 billion loan

Reported by pv magazine, pv magazine USA

Image: pv magazine USA

Construction has started on the first phase of the Big Rooter Power solar project in Robertson County, Texas, according to its owner, Panamint Capital. The site is Panamint's Twin Oaks power station, halfway between Dallas and Houston. The company says it will be the biggest solar build on a former coal mine in North America.

Panamint has closed the first phase of a $1.8 billion green loan. The $769 million first phase will fund Big Rooter West, a 491 MW section. More than $1 billion from the same loan will pay for Big Rooter East, a 658 MW second phase. The total project is described as 1.2 GW.

The project is built on reclaimed coal mine land. One source gives the area as 1,804 hectares, the other as 4,458 acres. Both say it connects to the Twin Oaks complex, which combines generation, surface mining, storage, data centre capacity and high-voltage transmission. The two reports also differ on the existing coal plant's size, giving 342 MW in one case and 349 MW in the other.

Panamint's chief executive, Apolka Totth, said the site will have 1.5 GW of thermal and renewable power when complete. She also cited over 20 miles of new 345 kV transmission, 1.6 GWh of battery storage and 790 MW of data centre capacity under development. The company has signed a long-term power purchase agreement with an unnamed corporation. It expects the two sections to create over 800 jobs.

Big Rooter East is due to start construction in December 2026 and enter commercial operation in August 2029. Financing for that phase is expected to close in the first quarter of 2027. Solv Energy will handle engineering and construction work. First Solar will supply about 2 million panels made in Ohio, Louisiana and Alabama. Nextpower will supply solar tracker systems, and over 34,000 tons of US-made steel will be used.

The reports do not name the buyer under the power agreement. They also do not give a completion date for the West section. Panamint, a Nevada-based firm founded in 2019, had 718 MW of capacity in operation in 2025, according to its sustainability report.

Enjoying this? Get the Energy brief

Every Friday: prices, subsidies and what changed in your market.

✓ Free · seven editions · one click to leave

Topics
Story continues on pv magazine USAAdd us as a preferred source on GoogleSee our stories first in Google’s Top Stories.